Solar panels: Do I need a building permit?

Solar panels on or at roof and facade, or free-standing. The table shows for every checked German state when the project is exempt from the permit procedure under the state building code. Each row leads to a detail page with provision and wording.

  • exemptThe building code lists the project as exempt without an open question of interpretation. The numbers are upper limits.
  • not clear-cutMatter of interpretation: it is not clear whether the provision applies to this project in this way. The calculator also shows “not clear-cut” here. The reason opens in the row.
  • not listed as exemptThe law does not list the project as exempt: a building permit is usually needed.
Solar panels: Do I need a building permit?
State Rule Height (m)Length (m) Provision
Baden-Württemberg exempt –– Anhang 1 (zu § 50 Absatz 1) LBO, Nr. 3 Buchst. c
Bavaria exempt + 1 variant –– Art. 57 Abs. 1 Nr. 3 Buchst. a BayBO
Berlin exempt + 1 variant –– § 61 Abs. 1 Nr. 3 Buchst. a und b BauO Bln
Brandenburg exempt + 2 variants –– § 61 Abs. 2 Nr. 3 Buchst. a und b BbgBO (Buchst. c: Satzung, als Variante)
Bremen exempt + 2 variants 39 § 61 Abs. 1 BremLBO, Nr. 3 Buchst. a und b
Hamburg exempt + 2 variants 39 Anlage zu § 61 HBauO, Abschnitt I Nr. 3 Buchst. a und b
Hesse exempt + 2 variants –– Anlage zu § 63 HBO, Abschnitt I Nr. 3.9.1 bis 3.9.3
Lower Saxony exempt + 3 variants –– Anhang (zu § 60 Abs. 1) NBauO, Nr. 2.3
Mecklenburg-Western Pomerania exempt + 3 variants 39 § 61 Abs. 1 Nr. 3 Buchst. a bis c LBauO M-V
North Rhine-Westphalia exempt + 2 variants –– § 62 Absatz 1 Nummer 3 Buchstabe a und b BauO NRW 2018
Rhineland-Palatinate exempt + 3 variants –– § 62 Abs. 1 Nr. 2 Buchst. e und f LBauO
Saarland exempt + 2 variants 312 § 61 Absatz 1 LBO, Nr. 3 Buchst. a und b
Saxony exempt + 1 variant –– § 61 Abs. 1 Nr. 3 Buchst. a SächsBO
Saxony-Anhalt exempt + 2 variants –– § 60 Abs. 1 Nr. 3 Buchst. a BauO LSA
Schleswig-Holstein exempt + 2 variants –– § 61 Abs. 1 Nr. 3 Buchst. a und b LBO
Thuringia exempt + 2 variants –– § 63 Abs. 1 Nr. 3 Buchst. a ThürBO

At a glance

16states checked
16of which clearly listed as exempt
3 mHighest value (Height)Bremen
3 mLowest value (Height)Saarland

How to read the table

The numbers are upper limits from the general rule of each building code. Variants, location, further conditions and the wording are on the detail page. Exempt does not mean free of rules: setback areas, the development plan, heritage protection and neighbour law still apply.

Check your own plot

Choose the state, enter the dimensions, get an answer with provision and wording.

Open the calculator

Frequently asked questions

Which state allows the largest solar panels without a permit?

According to the checked data, the highest value for height is in Bremen: 3 m. The lowest is in Saarland: 3 m. Variants, location and further conditions are on the detail pages.

Is a solar panels exempt in every German state?

No, each state regulates it on its own. Of 16 checked states, 16 list the project as exempt and 0 do not. The conditions of the respective state building code are decisive.

Do setback areas and the development plan still apply to an exempt project?

Yes. Exempt only means that no permit procedure is needed. The substantive requirements, for example setback areas, the development plan, heritage protection and neighbour law, still apply.